Merging Schedules w/ Different Planning Units
In the Open Standard
Kashyap MothaliMember for 21 years 6 months
- Created
- 3
- 1
0
I tried merging two P3 files - each with a different planning unit i.e., one has "Weeks" and the other has "Days".
I first copied the file with "Weeks" and changed it’s unit to "Days". I used this copied version as the host and brought in the file with "Days".
P3 did not convert the host file’s "Weeks" to "Days". The numeric value of the OD remained unchanged but with different units. This doesn’t serve me any purpose.
e.g., 1 week became 1 day and NOT 5 work days.
Is there a way to have P3 convert the OD automatically from weeks to days (assuming the default Cal #1)?
Thanks,
Kashyap
I first copied the file with "Weeks" and changed it’s unit to "Days". I used this copied version as the host and brought in the file with "Days".
P3 did not convert the host file’s "Weeks" to "Days". The numeric value of the OD remained unchanged but with different units. This doesn’t serve me any purpose.
e.g., 1 week became 1 day and NOT 5 work days.
Is there a way to have P3 convert the OD automatically from weeks to days (assuming the default Cal #1)?
Thanks,
Kashyap
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?