STW.P3 file

Yves TrudelMember for 21 years 2 months
Created
3
1
0
Hi every one,
I was amazed by the size of the STW.P3 file in my project: 103 Mo. It looks like this file would slow down my computer speed, and is a problem for e-mailing too.
All other files in the same project are around or less than 1000 k in size.
The overall number of activities is 2270
The project is a project group made of 4 sub projects
Anyone can help me?
Thanks a lot

Yves

3 replies

Oldest first
  1. 0
    Yves Trudel ·
    Well, it looks like nobody is aware of that.
    For the benefit of whomever may be interested, I erased that STW file and reopenned the project. Everything works fine and moreover, the STW file has been automatically regenerated to the size of...7 k!
    Ciao!
    Yves
  2. 0
    Ronald Winter ·
    The P3 documentation states; “P3 and Sure Trak use this file to store and communicate information when using a Sure Trak project in P3 or when using a P3 project in Sure Trak.” The file contains the following information

    o Project configuration information
    o Single default layout
    o Layout pointer
    o Activity priorities
    o Filters
    o Sure Trak resource dictionary information not supported by P3
    o Resource calendar information
    o Holidays for resource calendars
    o Sure Trak target dates
    o Outline codes
    o Sure Trak reports
    o Default activity codes.
  3. 0
    Yves Trudel ·
    Thank you for the information. I’m not the one who built that project, but I would be surprised if anyone would have worked with Suretrack in it. I’m inquiring.

    Thank you again

    Yves