Projects and project groups

Alexandre Faulx-BrioleMember for 23 years 8 months
Created
1
2
0
Hello,
I wonder if it is possible to connect an existing project to a group? There is nothing like this in the File New or File Overview dialogs.
I tried to copy and paste the tasks of the existing project to a blank project connected to a group, it seems to work randomly. Would fragnets be a better idea?
Thanks to all
Alexandre

1 reply

Oldest first
  1. 0
    Rashid Iqbal ·
    Make a new project and leave it empty. Then copy your current project under this new project group. This option is available under copy dialog box.

    Regards
    Rashid