Problems with different schedules
In the Open Standard
Marcio SampaioMember for 20 years 11 months
- Created
- 4
- 4
0
Hi, everybody.
I’m having a problem with both SureTrack and Primavera, which may be
basic, but that I cannot solve yet, even after following instructions
from manuals.
In a golf course construction project, most of my resourses work 8 hr
a day, but some of them (workforce) work 9 hrs a day.
I created a different schedule for these resources, showing 9 hrs a
day and 6 days a week, but even if the program asks me if I want to
re-calculate the costs, it will always show 8 hrs a day for all
resources.
Did I miss something?
Any help or tip would be very much appreciated.
Regards,
Marcio Eduardo.
I’m having a problem with both SureTrack and Primavera, which may be
basic, but that I cannot solve yet, even after following instructions
from manuals.
In a golf course construction project, most of my resourses work 8 hr
a day, but some of them (workforce) work 9 hrs a day.
I created a different schedule for these resources, showing 9 hrs a
day and 6 days a week, but even if the program asks me if I want to
re-calculate the costs, it will always show 8 hrs a day for all
resources.
Did I miss something?
Any help or tip would be very much appreciated.
Regards,
Marcio Eduardo.
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?