Problems with different schedules

Marcio SampaioMember for 20 years 11 months
Created
4
4
0
Hi, everybody.
I’m having a problem with both SureTrack and Primavera, which may be
basic, but that I cannot solve yet, even after following instructions
from manuals.
In a golf course construction project, most of my resourses work 8 hr
a day, but some of them (workforce) work 9 hrs a day.
I created a different schedule for these resources, showing 9 hrs a
day and 6 days a week, but even if the program asks me if I want to
re-calculate the costs, it will always show 8 hrs a day for all
resources.
Did I miss something?

Any help or tip would be very much appreciated.

Regards,

Marcio Eduardo.

4 replies

Oldest first
  1. 0
    David Moses ·
    Dear friend,

    why dont you try to create two different calendars.one for 8 hrs a day and the other for 9 hrs a day.

    I hope this will help.
  2. 0
    Marcio Sampaio ·
    Thanks a lot ... but read again:

    "I created a different schedule for these resources, showing 9 hrs a
    day and 6 days a week, but even if the program asks me if I want to
    re-calculate the costs, it will always show 8 hrs a day for all
    resources."

    Regards
  3. 0
    Joao Ribeiro ·
    In Suretrak, I think you must change the activity type to "Independent", in P3 I don´t remember now, but there is something similar with other name.
    Anyway, I think the cost will be the sum of eight hour of one resource with the nine hours of the other (if both work on the same activity).

    Cheers.
  4. 0
    Marcio Sampaio ·
    Thanks Joao Ferreira ... think it’s going to help.

    Best Regards.

Log in or join to reply