Resource Commitment in P3 version 3.1
In the Open Standard
Donny MartinezMember for 21 years 1 month
- Created
- 2
- 2
0
Could anyone of you help me please on the following:
Activities:
1. Building Construction, dur:6mths, resources:Snr Project Engineer 70% for the first 3 months and Project Engineer 100% throughout
2. Road Construction, dur: 8mths, resources: Snr Road Engineer 80% for the first 2 months and Road Engineer 100% from month no 3 onwards till completion.
And so on..
Provided I’ve entered all the appropriate info above into P3 (i.e.: activity codes, durations, sequence, resources, etc):
How do I allocate that 70% of Snr Project Engineer time onto the activities? (We can do this in MS Project via ’Resource Usage’ option).
Thanks alot guys
Regards
Donny
Activities:
1. Building Construction, dur:6mths, resources:Snr Project Engineer 70% for the first 3 months and Project Engineer 100% throughout
2. Road Construction, dur: 8mths, resources: Snr Road Engineer 80% for the first 2 months and Road Engineer 100% from month no 3 onwards till completion.
And so on..
Provided I’ve entered all the appropriate info above into P3 (i.e.: activity codes, durations, sequence, resources, etc):
How do I allocate that 70% of Snr Project Engineer time onto the activities? (We can do this in MS Project via ’Resource Usage’ option).
Thanks alot guys
Regards
Donny
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?