Guys need your help,

How can i show plan percentage from P3?
And How can i be delayed in progress let say 50% if we think and the actual delayed is only 10 percent hence
on the schedule is we are not that too far.
Is there a bug in P3?

Thanks in advance guys

wilfred

1 reply

Oldest first
  1. 0
    Paul Harris ·
    On way is take a copy of the original project and autostatus it using Progress Spotlights. This schedule then may be shown as a second target and Target 2 % Complete displayed.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au