Generate Plan % from P3
In the Open Standard
uid 0
- Created
- 1
- 3
0
Guys need your help,
How can i show plan percentage from P3?
And How can i be delayed in progress let say 50% if we think and the actual delayed is only 10 percent hence
on the schedule is we are not that too far.
Is there a bug in P3?
Thanks in advance guys
wilfred
How can i show plan percentage from P3?
And How can i be delayed in progress let say 50% if we think and the actual delayed is only 10 percent hence
on the schedule is we are not that too far.
Is there a bug in P3?
Thanks in advance guys
wilfred
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?