Suretrack - Creating Tabular Resource Loading Report

Rual BritsMember for 21 years 10 months
Created
1
5
0
Hi there,

I use Primavera 3.1 primarily and have to help another planner (trainee) to draw up an s-curve, but she uses Suretrack 3.0.Normally I use Tabular Reports||Resource||Loading to do the report for excel(Resources spread over timeperiod). How would I do that in Suretrack? I have never used Suretrack before and I am having some trouble in getting the report we need for the s-curve.
Any help would be appreciated. Thank you guys in advance.

1 reply

Oldest first
  1. 0
    Paul Harris ·
    To export to excel use the Tools, Wizard, Pivot Table Wizard, it may take a bit of time to run with a large amount of data.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au