How to allocate discrete resource?

Xifan XieMember for 22 years
Created
1
2
0
Anyone knows about how to allocate discrete resource in P3? I found the resource curves are sucessive distribution in p3. But i want to put discrete resource, for example, a worker works for 2 days and then stops for 3 days and works again for 4 days and then stops for 2 days. Thanks a lot.

1 reply

Oldest first
  1. 0
    Katalin Hovanyi ·
    Haliho,
    Try to use the resource calendar.
    Best Regards Katalin