P3 Activity Description field - how much i can write??

James SaldigorMember for 20 years 4 months
Created
8
1
0
Dear All Planners,

I am a beginner in Planning using P3 and i am starting to input the my first few activites in my programme. I noticed that the activity description field can accommodate about 47 characters although the coulmn width can be adjusted to your preference.

Is there any way to increase the characters i can input in the field or any "wrap text" function just like in excel. Or any way to resolve my longer activities.

I hope anybody can help,

Thanks

8 replies

Oldest first
  1. 0
    Santosh Bhat ·
    The activity description length is limited.

    You can add upto 99 log texts to each activity and then display them either left or right of the activity bar. It just gets messy.
  2. 0
    Ronaldo Quilao ·
    My suggestion is: as much as possible write the most precise description of your activity. Simple description which everybody can understand is the best. Try it!
  3. 0
    Dayanidhi Dhandapany ·
    use abbreviated words to describe the activities in a meaningful way.
  4. 0
    James Saldigor ·
    Dear All Planners,

    Thanks for all your replies,I have applied your suggestions, Thanks again,

    Cheers,
    JS
  5. 0
    Zhang Haixiang ·
    48 characters,for some language only 24 characters (e.g. Chinese)
  6. 0
    Shahzad Munawar ·
    Better to describe activity in a manner which can be easily understood by each one easily . I think not consisting of more than 50 characters
  7. 0
    Brij Patwari ·
    Hi James!!
    In my P3 Version 3.0, I am not able to write more than 48 Characters. So, I Thnik for that version 48 characters is the limit.

    Regards,

    Brij Patwari
    Project Control (EPC),
    Reliance.
  8. 0
    James Saldigor ·
    Hello all great planners,

    It’s been sometime since i went away and studied this thing we called primavera project planner to a deeper level.

    This primavera is indeed a powerful tool yet there is a long way for me to easily maneuver skillfully with this so i can put my most project control with it.

    I thank you all guys for all your kind replies.

    Cheers,
    james

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?