Hi All,
As per my knowledge, P3 can export an Excel file with Successor relationships.
Most of the time in Construction projects it is very difficult to define relation based on successors. As there could be many and v might miss out some.
Can anyone guide, if there is any option (and if yes, what is the syntax for it) v can export Predecessor realtionships also??


Regards,

Brij Patwari
Project Control Engineer (EPCC)
Reliance - Jamnagar Refinery.

1 reply

Oldest first
  1. 0
    Zhang Haixiang ·
    Actually they are the same.
    export your successor relationships to excel,
    then change change the two columns
    then you get want you want ’predecessor relationship’