resource calendars

Benny LamMember for 20 years 3 months
Created
2
1
0
Dear All Planners,

I am starting to creat a AON network in P3.

The network’s detail:
- only one type of resource: Labour
- total amount of resource = 4


Question 1:

Could I set different resource calendars if i just use one type of resource???

Calendar 1 --> first 2 Labour (i.e. Labour 1 & 2): 6 working days/week (from Monday to Saturday)
Calendar 2 --> last 2 Labour (i.e. Labour 3 & 4): 5 working days/week (from Monday to Friday)


Question 2:

Case 1 (both 2 calendars)
If a activity requires all labours, the working days should be 5 working days/week

Case 2 (calendar 1 or 2 only)
If a activity just requires one or two labours, the working days should be depended on their own calendar (5 or 6 working days/week).


Is there any way to automatically arrange the number of resources for each activity, no matter what the resource calendar is involved???

I hope anybody can help,

Thanks!

2 replies

Oldest first
  1. 0
    Paul Harris ·
    Question 1

    Benny

    Each resource may only have one calendar. For the resource to schedule with a calendar it must be Independent or Meeting Task Type.

    Question 2
    You may use Global change to change the quantity o resources. You need to understand the Autocost rules before you use this function.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  2. 0
    Benny Lam ·
    Paul,
    Thanks for your kind help.