Resource relationship within a task
In the Open Standard
Redzuan SamsudinMember for 20 years 3 months
- Created
- 6
- 2
0
Good day to all
It was a relief that I found this forum!!! It is very helpful. Thank you all for your contribution.
My questions is:
Can we link many resources for a single task. Example:
Task = Install & Check Pipe Spool.
Resource use = Rigger, Pipe Fitter, Pipe Welder, Firewatcher, NDT
My guery = Can we link above resources in the task. Rigger SS Pipe Fitter FF Pipe Fitter FS NDT.
Hope you all understand my question.
Thanks & regards.
It was a relief that I found this forum!!! It is very helpful. Thank you all for your contribution.
My questions is:
Can we link many resources for a single task. Example:
Task = Install & Check Pipe Spool.
Resource use = Rigger, Pipe Fitter, Pipe Welder, Firewatcher, NDT
My guery = Can we link above resources in the task. Rigger SS Pipe Fitter FF Pipe Fitter FS NDT.
Hope you all understand my question.
Thanks & regards.
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?