I did a cotation using an excel sheet, now that we have the contract, I need to import that sheet in P3.
In my cotation I have these informations:
-Activity number = ACT
-Task description = TITLE
-Ressource (trade) = RES
-Number of ressources = UPT
-Total hours of the task = BQ
-Duration of the task = OD
I want to import the data in P3 (the ressource quantity must driven the OD, and BQ must be fixed). (Ressource qty x OD = BQ ???)
Can you tell me the headers to write in my excel sheet?
In my cotation I have these informations:
-Activity number = ACT
-Task description = TITLE
-Ressource (trade) = RES
-Number of ressources = UPT
-Total hours of the task = BQ
-Duration of the task = OD
I want to import the data in P3 (the ressource quantity must driven the OD, and BQ must be fixed). (Ressource qty x OD = BQ ???)
Can you tell me the headers to write in my excel sheet?
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?