PROJ environment variable is too long

Svein MyklebustMember for 20 years 4 months
Created
4
1
0
Get the message:
PROJ environment variable is too long
when running Global Changes.

The network is imported via MPX.

Any experience?
Any ideas?

Svein

4 replies

Oldest first
  1. 0
    Praves Suppa ·
    Hello Svein Myklebust,

    it might be a causing your project directory whether some of them has more than 8 characters.


    Hope can help you more or less.

    Best Regards,
    Praves
  2. 0
    Raja Izat Raja Ibrahim ·
    Hi,
    try to find from the old post thread. The problem is because the file u use is under sub directory to another make it under one sub directory only.
  3. 0
    Svein Myklebust ·

    Thanks for the answer.
    The problem was that the path to the project was to long.

    Old treads are not easy to find these days.
    The search engine is down.

    Svein
  4. 0
    Ronald Winter ·
    The bottom line is that your total disk:directory\file name cannot be longer than 64 characters. Look here for an earlier forum on this subject. Good luck!