Resource Leveling Need Help

Michael CraigMember for 20 years 7 months
Created
2
3
0
I need to maintain the Resource Leveled dates and I want to know what to expect when I resource level and turn off the option to ’Preserve scheduled early and late dates". Please in you have any information on this I would greatly appreciate it if you could post it back to me.

No one in my dept knows much about resource leveling!!!

Thanks
Michael

2 replies

Oldest first
  1. 0
    Michael Craig ·
    I should have clarified sorry I’m talking about P3E 4.0

    Thanks
  2. 0
    Ronald Winter ·
    P3ec has two places where dates can go, early dates and planned dates. When you perform a CPM analysis, the calculations go into the early dates section. When you do a resource leveling, the new leveled dates go into the planned dates section. The leveled dates will also go into the early dates section unless you use the option that you asked about. Good luck!

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?