Splitting / Suspend /Resume Activity

Felis MuhammedMember for 20 years 2 months
Created
2
1
0
Hai all,

Is it possible to split an activity in P3 the way we do in MS-project?? Also how to suspend and resume an activity.

Appreciate your response.

Regards

Felis

2 replies

Oldest first
  1. 0
    Karim Mounir ·
    Splitting : select the activity u want and right click on it and select Dissolve / Extract.

    Press F7 to show the bottom activity form
    Suspend / Resume : select the activity in which u want to apply suspend or resume date then click on "Dates" then select the "Suspend" or "Resume" date.
  2. 0
    Christian Adrian De Vera ·
    using "suspend and resume date" should be dealth with caution, you can only use it on an activity which is active and has been affected with arising events not to prolong the schedule...

    Cheers...