I get the message ’PROJ environment variable is too long’ and this is preventing me from scheduling my P3 programme. Can anyone suggest a solution ? Thanks in advance.

Raja

3 replies

Oldest first
  1. 0
    Abhijeet Ranadhir ·
    The name of the directory folders where you save your file should not be longer then 4 characters. If you have your file in D:/Schedules/projects/cpm.prx it should be D:/Sche/proj/cpm.prx.
  2. 0
    David Moses ·
    Hi there,

    This has been discussed several times before...

    This happens when you store your project files in a deep directory (consisting of multiple levels of subdirectories).

    Simply save your project files to a directory consisting of only a few levels.

    for example => C:\P3WIN\PROJECTS

    I hope this helps..
  3. 0
    Ronald Winter ·
    Look here for more information. Good luck!