resource levelling

John MossMember for 22 years 8 months
Created
3
1
0
Hi

I am trying to resource level and have assigned a max and normal limit to a driving resource. I want a max limit greater than 9999, but P3 does not seem to allow an input greater than 4 digits long. Anyone had this problem ?

Thanks

John

3 replies

Oldest first
  1. 0
    David Kelly ·
    John,

    I’ve always just divided the resource requirement and the resource availablity by a factor of 10.
  2. 0
    Paul Harris ·
    There are a couples place in P3 where there is a 9999 limit including activity duraton which restricts the total duration of a project.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  3. 0
    John Raper ·
    John

    Have you tried dividing by 8 or 40, and showing the time window in days or weeks?

    Hope this helps
    John R