Is there a restriction on the number of tasks that can be imported from MS Project to P3e.

3 replies

Oldest first
  1. 0
    Marcio Sampaio ·
    The maximum I did had 15.000 activities.

    I think there is no restriction.

    Regards.

    Marcio Eduardo.
  2. 0
    Alex Wong ·
    The quick answer is NO

    But... you know that is coming...

    In P3e, it does drive a lot of resources especially if you use Oracle or SQL server to drive P3e. As a result, the number of importing or exporting is very dependent in the Memory. Both virtual and Physical Memory. My suggestion is you must at least have 2 G memory (RAM) to operate P3e
    Ideal case is 4G

    (BTW you posted this in the wrong forum topic)

    Cheers

    Alex
  3. 0
    Davie Ross ·
    Thanks for your help I think the problem is RAM. I have managed to import 5000 activities at a time no problem.