line showing the project completion date in the Bar cha

Haresh JayanthMember for 20 years 1 month
Created
2
2
0
Can we create a line showing the project completion date in the Bar chart area in primavera 3.1?

2 replies

Oldest first
  1. 0
    Steven Oliver ·
    Have a look in the Help, for "Curtain".

    From memory, the curtain toolbar is accessed from View, Attachments.
  2. 0
    Alex Wong ·
    Gents

    You can also display what we call the activity progress line in the bar chart to indicate any ahead and delay progress

    Alex