How to change the starting date of a project

Javier F. Via GiglioMember for 20 years
Created
6
68
0
Hi,
I’m new in Primavera and maybe my question is very simple and basic.
I didn’t find how to change the starting date of a project. I made a program for a project (WBS, dates, duration, resources, etc.) but yesterday the project manager told me that the project was delayed one month.
I guess I can move the whole activities in one step (like in MS Project), maybe using Global Change? What happend with the resources?
Can you help me?
Many thanks in Advance.

6 replies

Oldest first
  1. 0
    Paul Harris ·
    Select File, Project Overview and set a new start date.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  2. 0
    Javier F. Via Giglio ·
    Thank you Paul.
    I did what you suggested, but only the reference start date line was moved and the other details remained as before.
    I don’t want to keep the original programme as reference (with a month of delay), the idea is to have a new programme that will start with a month of difference from the original plan.
    Maybe I have to do another step.
    If you have more suggestions I’ll be glad to try them.
  3. 0
    Christian Adrian De Vera ·
    Javier

    If I understood you correctly what you want is to have a new schedule that will show a delay of a month, if this is the case you should backup your original schedule (for reference) then adjust the current schedule start date to your new start date then change your data date equal to your new start date and reschedule it... for adjusting the reference start date line kindly refer to mr. Paul’s suggestion...

    HTH

    Christian
  4. 0
    Kumar Raja ·

    Let me clear ur doubt in

    Let me clear ur doubt in Primavera Latest Version 8.2

     

    Open Primavera ! Select  " FILE" close all the Projects which are Opened 

    Go to Enterprise Select the Project for which u want to change the start date of the Project 

    Right Click on the Project Select option "Project Details" from Down

    Select it twice if u did not get the details in first attempt 

    then u can able to see the--- show bottom view tabs .. 

    in that select the tab " DATES" and change the date what ever u want .. that's it ur done 

     

    if u did not follow this process directly changed the actual start of the first activity it will be converted in to Constraint. 

  5. 0
    Zoltan Palffy ·

    wrong section of forum

    wrong section of forum

  6. 0
    Farnas Ap ·

    after Creating the

    after Creating the projet.Close the entore priamvera and open it again.Clik our projeCt whih one to Change.

    then replae on dates(before entering to the projet)

    its helpfull only if before the baseline reation.

     

     

     

Log in or join to reply