remainging duration

Tahir Naseem PMP, CCEMember for 19 years 11 months
Created
2
1
0
Hi guys
I have a problem regarding reaming duration. P3 calculate RD based on progress achieved / planning unit up to data date and then suggest the duration for balance progress. Some time this become very illogical due to less physical progress in long duration. When I try to reduce the RD and reschedule but RD become again the same what P3 suggest. Please guide in detail. May be there is any problem in auto cost rules.

Regards
Tahir

2 replies

Oldest first
  1. 0
    Mohamed Thabet ·
    Hi,

    To update separately the remaining duration & the activity % comp. Just uncheck from the auto cost rule "Link remaining duration & schedule percent complete"

    But then you have to update remaining duration for all the schedule activities manually.

    Regards,

    Moe
  2. 0
    Tahir Naseem PMP, CCE ·
    Dear Mohammad
    I already try this option but not working. Thanks for reply. I found the mistake there is some mistake in logic that why the remaining duration was calculate after the FS of predessor activity where as this should be FF with a counted lag.
    Thanks again for quick reply.
    Regard
    Tahir