Resource loading based on late dates.

Tahir Naseem PMP, CCEMember for 19 years 11 months
Created
4
1
0
Dear All

I prepared S-curve in excel after getting resource loading report from P3 because client need some makeup & good looking format. Any how this will not affect on data. My problem is that this resource loading available only based on early dates. I want to prepare the same for late dates.
For the graphical report P3 provide the both but for the tabular report has this limitation. If some one has any idea / solution to guide me.
Regards
Tahir

4 replies

Oldest first
  1. 0
    David Kelly ·
    You will have to use a global change to set all the early dates equal to the late dates before running a Load Report.

    An alternative I have used in the past is to add a zero-free-float constraint to every activity and schedule before running the load report. This gives the "late as possible" data, which might be as interestin g as the "late" data.
  2. 0
    Tahir Naseem PMP, CCE ·
    Dear Kelly
    your first suggestion is good and practicle without any impact to your current schedule.
    I did it and got the result. i will explain for the others
    Make a copy of current schedule
    apply global change
    run the resource loading report.

    Thanks again a lot for the help
    Regards
    Tahir
  3. 0
    Eugene K ·
    HI all,

    just to share, alternatively you can generate a res.tabular report and select BOTH early and Late dates (or just LATE if you only want late dates).

    the major diff is that is gives the time period in rows, then just copy/paste the values into excel.
  4. 0
    Dayanidhi Dhandapany ·
    A piece of advice, store Early Start and Early Finish dates in Custom Data Items(CDI) defined variables Planned Start(PLST) and Planned Finish(PLFN) before making changes to store the late dates(LS/LF) info into early dates(ES/EF), then it will be easy to transfer back early dates info (once the required job has been done)from the stored CDI variables to Early Start and Early Finish dates.

    HTH