Duration Summary

Weni SamsonMember for 19 years 11 months
Created
2
1
0
Hi there! Can anyone help me on how to put a duration summary per activity codes or per WBS or per level? I am trying to put a summary duration on each level so that it would be easier for me to identify the complete duration of each level. Thank you with much appreciation.

2 replies

Oldest first
  1. 0
    Jose Frade ·
    Hello,

    Several options depending on how you organised the sturcture of your project.

    Option 1 WBS

    Imagine you created a wbs code like this
    10. Engineering
    10.10 Basic
    10.10.10 Process flow Diags.
    10.10.20 Layout
    10.20.30 etc

    then you have to attribute to each activity one of this codes.

    After, you can create one activity type (example) WBS with code 10.10 - this activity will summarize all activities under code 10.10 .

    Option 2
    Summarize by layout
    in the stucture of your database create the necessary codes for the summary phase you want (Eng. / Procurement / manufacturing / transport / construction / erection / commissioning / etc).

    Then sort the activities by phase code and ask to have the summary bar (top or bottom).

    I hope to have been of any help.

    BR
    JMFrade
  2. 0
    Alex Wong ·
    Jose

    You may be left out the third option "Hammack Activity" and this may be one of the best option

    Why
    WBS you cannot link a relationship to the summary, and it a rigid structure so once setup its very hard to change the level

    Code structure in Layout
    Yes it is very flexible, but again you cannot link the summary bar with the actual activity.

    So my suggestion is depend you need Code structure and Hammack is you best options

    HTH

    Alex