I need help.

I have to plans one is target and other is current in P3 ver 3.1. I want to filter the activities in the current project of the target project within period range.

Have anyone some bright idea. I searched a lot, this facility is not available in this version. Am I right?

Shahab

5 replies

Oldest first
  1. 0
    Shahab Ali ·
    I need help.

    I have two (2) plans one is target and other is current in P3 ver 3.1. I want to filter the activities in the current project of the target project within period range.

    Have anyone some bright idea. I searched a lot, this facility is not available in this version. Am I right?

    Shahab
  2. 0
    Prabin Kumar ·
    I tried like this!

    First I added a new activity code(say ’tar’) to the current project and then opened Global change, feeded the logic with Target early start/target early finish with respect to duration (if logic is true - add ’tar’ EQ ’F’ else ’blank’)
    After running the global change, filtered the activity having ’tar = F’

    thanks,


    Prabin Kumar
  3. 0
    Alex Wong ·
    Probin

    I dont think you can use global change with targeted dates as a condition(correct me if I am wrong)

    My suggestion is
    create a CDI call PF - PS (Normally it is already created)
    export your target schedule ES EF
    export your current schedule with PF & PS
    Replace PF and PS with target ES and EF
    Import back to your current schedule

    from this date onward you can filter all your plan date (Target) and dont need to use global change

    Good Luck

    Alex
  4. 0
    Prabin Kumar ·
    Alex,

    Yes, your idea is quite good and its easy also.
    For the global change with targeted dates as a condition I still wish to insist that its possible.
    After opening ’Data item’ for writing a condition, select Target data, choose T1ES /T1EF/T2EF/T2EF....,whatever suits to the condition and run..

    Am I wrong ?

    I had tried this !

    Prabin
  5. 0
    Shahab Ali ·
    Thanks! both guys

    Now I remembered, I did same thing 2 years back as Alex said. I needed two weeks look ahead filter on target programme while opening current progamme. In my case Alex idea is the easiest one.

    Thanks once again

    Shahab