managing multiple projects in P3

Morph TMember for 20 years 2 months
Created
6
2
0
hello all

happy new year for all planners, specially who are not with their families.

how can you manage a group of projects in P3, with different resources unit prices for each project as each one is located in different geographic location( a hint; in my country whenever you go south it become more expensive)

friendly mimoune

6 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Hi mimoune,
    You could 1st use hierarchical resources, and give each "sub"resource a specific price; e.g. Mimoune-North will be allocated to activities occuring in Algiers with a unit rate of 1000 and Mimoune-South to activities in the south with a rate of 1500, both being part of the "super"resource Mimoune*
    Or if the resource is working Noth or South depending of time, use the "through" column to define the period of time during which the unit rate is used.
    IMOO, 1st solution is the best.
    Cheers, 3aïd el kheir, 3âm el jedid 3âme el kheir
    Alexandre
  2. 0
    Alex Wong ·
    mimoune

    is this your second account?? ...

    Anyway our french friend give you a solution in P5 not P3 where there is NO hierarchical resource in P3.

    To help your problem I suggest to use name resource (if the resource pool is not hugh)
    If there is large quantity of named resouce then you can have Resource A and Resource B both have the resouce code of X. as a result you can use the resouce code to do filtering, sorting, grouping ....

    HTH

    Alex
  3. 0
    Morph T ·
    hello

    Thanks for your replies, actually i have two accounts, i meant to use one for regular questions, and the other for not political correct question like asking for jobs, or moaning about our company

    But I had made a stupid mistake, by posting a normal question (with my real name) in my not normal account!

    Anyway, what are the advantages (if any) of using P5 au lieu of P3 in managing a single project



    Friendly yours
  4. 0
    Alexandre Faulx-Briole ·
    Alex Wong,
    Happy New Year ...
    Regarding hierarchical resources in P3, you should read the technical litterature about it; look at P3 Planning and Control Guide, pages 109 and 110: use a wildcard to create hierarchical resources, as follows
    EPG* = All programmers - employee
    EPG1* = Sr. programmers - employee
    EPG1CTM = Conrad T. Mayer sr. programmer
    Cheers, alexandre
  5. 0
    Alex Wong ·
    Alexandre,

    Thanks for the clarificiation, but I think this resource setup is not a true hierarchical structure, especially in Resource Leveling it become impossible to level these resource base one the structure and this is where the original question is based on. Can you share with us how to manage this in a multip projeect environment. Thanks in advance

    Cheers

    Alex
  6. 0
    Alexandre Faulx-Briole ·
    Alex,
    1. both Primavera Corp and Paul E. Harris describe this resource setup as "hierarchical"; I agree that PM4/5 or AstaDev PowerProject resource setup, or MS Project Server Resource Breakdown Structure look "more hierarchical"
    2. to answer directly Mimoun’s question: can you imagine any piece of software easily understand that the same "Mimoun" will cost less or more depending the project he is working on?
    Should I have to prepare resources to work that way, I would create several resources with quite similar names, e.g. Mimoun-South at $200 and Mimoun-North at $150, and use the so called hierarchical resource functionnality to make sure that the "real" resource Mimoun is not overallocated.
    This would work the same between different tasks in the same project or between different projects in the same group.
    I hope this will help
    Alexandre

Log in or join to reply