Resource Loading Tabular Report

John MossMember for 22 years 8 months
Created
3
1
0
I am have a lot of problems producing a loading for a resource in the Tabular report - resources - resource loading reports - RL03 Resource loading activity summary.

For some strange reason the total resource spread each year is not the same as the BQ in the P3 file or total in the toal column and the shape of the spread per year is not as per the resource ID curves specified.

Any clues ?

Thanks

3 replies

Oldest first
  1. 0
    Alex Wong ·
    Hi John

    Long time no C, how are u!!

    The reason there is a different between the S-Curve (BQ in the table you see in the layout format) and the tabular report is because they use different baseline plan quantity.

    I have this problem b 4, what you need to check is your target plan budgeted quantity and your current plan budgeted quantity. if they are different they will produce a different result between the tabular report and the P3 layout resource table.

    HTH

    Alex
  2. 0
    Nicolas Berger ·
    The problem is probably because of changes on BC without changing Cost at Completion as well.
    Means that you should have some Variance in your Cost or Qty...
  3. 0
    Alex Wong ·
    Hi John

    If you can post your screen print, I might able to help

    Cheers

    Alex