Updating Price/Unit

Imran MalikMember for 22 years 4 months
Created
3
2
0
Hi!
Is there some way to update/change price/unit of resources using import export and/or global change because it takes time to update prices one by one but in export price/unit is not available in p3
Thanks in advance

3 replies

Oldest first
  1. 0
    Andrew Podolny ·
    Hi there.

    Sure you can - check the \support directory on your P3 installation CD for ProjectMod.XLS file. There is self explanatory sheet in this workbook named ’Login’.

    Good luck
    Andrew
  2. 0
    Imran Malik ·
    Thanks that works for exporting but how to import it back after editing; in Primavera to get resource dictionary updated. I tried to save sheet in WK1 format and import but it gives error id. Please help
    Regards
    Imran
  3. 0
    Imran Malik ·
    Oh oh its done thank you very much