multiuser simultaneous edit in a single project

Keyel IsorenaMember for 19 years 11 months
Created
2
1
0
just wanted to know if it possible to have 2 or more users edit a single project save on a network folder, if it is, how? thanx in advance

2 replies

Oldest first
  1. 0
    Jose Frade ·
    Hello,
    Yes it is possible (even more users). For that you need:
    1. To have the project as multiuser.
    2. To have enough licence numbers available (at least two for your example of two planners) to open Primavera for boths planners.
    3. None of the users can open the project as exclusive.

    With the above you can open the projects with as many licenses as you have.

    BR
    JMFrade

  2. 0
    Alex Wong ·
    the only restriction is you cannot edit the same activity at the same time

    Good Luck

    Alex