Relationship Lines have gone????

James KendrickMember for 19 years 7 months
Created
1
3
0
Im not exactly a novice user on Primavera P3, but I have a rather confusing problem at the moment???

The relationship lines will not appear? the programme is made up of an estimate 1000+ activities, But the the activity(F3) option in the menu is greyed out???? the software will allow me to compile predessors and successors, but I cannot seem to do this on the gantt chart I have to update this longhand in the pull down menus. But I still cant ""access"" to the relationship(f3). Anybody any ideas, I have a programme update to complete by wednesday.

Best Regards

Jim

1 reply

Oldest first
  1. 0
    James Kendrick ·
    It ok Ive sussed it, On the format bars option if you have the bars displayed as "necked" this subsequently results in the logic links not being displayed. Not sure why, but hey Ive figured it out now.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?