SureTrak - Late dates / S- Curves
In the Open Standard
T M HarishMember for 23 years 2 months
- Created
- 2
- 1
0
Dear Friends,
Can someone help me on the problem I am facing on SureTrak.
After resource loading, I want to use the periodic data for S-curves, which I could get for the early dates.
Is there any way I could get the periodic data for late dates, same like P3. So I will have two curves, early planned curve and late planned curve.
Regards,
Harish
UAE
Can someone help me on the problem I am facing on SureTrak.
After resource loading, I want to use the periodic data for S-curves, which I could get for the early dates.
Is there any way I could get the periodic data for late dates, same like P3. So I will have two curves, early planned curve and late planned curve.
Regards,
Harish
UAE
2 replies
Oldest firstLog in or join to reply