SureTrak - Late dates / S- Curves

T M HarishMember for 23 years 2 months
Created
2
1
0
Dear Friends,

Can someone help me on the problem I am facing on SureTrak.

After resource loading, I want to use the periodic data for S-curves, which I could get for the early dates.

Is there any way I could get the periodic data for late dates, same like P3. So I will have two curves, early planned curve and late planned curve.

Regards,
Harish
UAE


2 replies

Oldest first
  1. 0
    Eckart Schenck ·
    scheduling backwards should give you late data, I suppose.
  2. 0
    José Garrido ·
    Hi, this is my first post reply

    I will explain since(as,like) me I solve this problem.

    First, inserted a column with "Constraint Finish Type"
    Second, I select in the first activity "Constraint Finish Type = As late as possible".
    Third. Whit "Copy Cell" I drag on all the activities and with "Paste Cell" paste in all the "As late as possible" value, for the column "Constraint Finish Type".
    Last. I calculate this new situation and the result is the late curve.

    I expect to have solved your problem.

    I ask for excuses for my English, but only I write Spanish and to write this message have used a translator.