Skip to content

Suspension Dates on P3

Forum GuestMember for 17 years 8 months
Created
8
3
0
Dear Experts,

Suspension Dates for some projects occurs more than once...maybe twice or more...

But in P3, i think it can only be recorded once (am i right?)...how would you deal with it when the project have some suspension more than once?

Hope to solve this kind of problem..

Thanks alot

Alfon
SCDC

8 replies

Oldest first
  1. 0
    Clarence Choi ·
    I believe your down times should have reasons for that.
    Options:
    1. sub-divide your activity into avtivities.
    2. create a new calendar and assign the down time as non-working dates in the calendar.
    Hope this will help.
  2. 0
    Forum Guest ·
    You should be seperately recording each and every occasion where for no fault of your own you are unable to proceed.

    This gives a full record of interruptions to the work and is invaluable if you needed to prepare a claim.
  3. 0
    Luca Basile ·
    I am agree with Choi, is not that You have to put several suspension and resume because Your schedule is to high level?
    If not split down it in any case in different activities, put before a milestone with an "self explaning" start milestone taht will help You later on in the possible preparation of the claim.
    To group the activities resulting from this splitting use the coding structure.
    When You just put suspend and resume you loose the reason, I prefer to split and put self explaining milestone.
  4. 0
    Alfon Lyndon Joson ·
    tx alot guys and best regards....


    ALFON
    SCDC
  5. 0
    Gayantha Abeywardena ·

    Dear All,
    I want to show the suspension of activity four times due to obstructions. as we are using P3 please tell me a way to show this in a program its single activity (placing conduite)

    GA
  6. 0
    A D ·
    you can show suspended activities by pressing F7 --> DATES Tab --> Suspend date and resume date

    We cannot show suspension activities in baseline program. In updated program, it must have actual date.

    But, activity suspension for four times......? I dont think so, its possible in P3. You can show it only once, I believe.

    Cheers,

    Rav
  7. 0
    Gayantha Abeywardena ·
    Hi Rav

    I followed your steps but no changes in the bar how does it appears????? will version 5 helps ....

    GA
  8. 0
    A D ·
    Go to Bars and make sure NECK is under visible mode.

    If neck is unchecked, then it will show a straight bar.

    Cheers,

    Rav

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?