project too long
In the Open Standard
Richard LawsMember for 19 years 7 months
- Created
- 4
- 1
0
I have a problem when I schedule my project. It says "Calendar problem detected, Your project is too long for the calendars." and then puts the activities causing this at a fixed end point. I have deleted these activies but still get the same message. I have tried changing the start date of the project to a later date with no luck. Right now the plan is ok but I need to start putting in activties that will go beyond the fixed end point. Does anyone have any ideas on how to get around this?
Thanks
Richard
Thanks
Richard
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?