project too long

Richard LawsMember for 19 years 7 months
Created
4
1
0
I have a problem when I schedule my project. It says "Calendar problem detected, Your project is too long for the calendars." and then puts the activities causing this at a fixed end point. I have deleted these activies but still get the same message. I have tried changing the start date of the project to a later date with no luck. Right now the plan is ok but I need to start putting in activties that will go beyond the fixed end point. Does anyone have any ideas on how to get around this?

Thanks
Richard

4 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Richard,
    each project group has a global calendar with a certain duration DATA-->Calendar-->Global--> Standard. If your project needs more time, the calendar will automatically adapted; but only to a certain maximum which depends on your planning unit. Check the start date, which I often found being too early and set it to one period before the project’s start.
    If this will not work, you’ll have to modify the planning unit by creating a new project group and copying the project.
    Calendar’s limit is due to the fixed record format of the betrieve-database.
    Regards
    Dieter
  2. 0
    Paul Harris ·
    P3 allows 9999 planning units. It is something like this and maybe an expert will let us know exactly how it works. Depending on if you are using daily calendars on 24hrs/day you will be restricted to a schedule of just over a year; 9999/365/24. On the other hand a 7day/ week on a daily calendar will be restricted to 27 years 9999/365.

    You can always crib a bit of time by moving the project start date up behind the data date as the project progresses as P3 ignores Actual Starts in calculation.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au
  3. 0
    Richard Laws ·
    Thanks for your help. I thought it might be a limited number of planning units. The plan is hours.

    I did this as I wanted to have resource calendars for individuals working a shorter week.

    I will move the plan to a day unit version. I half-heartedly tried to do this some time ago but gave up when I found it did not change all durations automatically. I can see from some other posts here that I should be able to do that if I put some real effort into it.

    Again, many thanks.

    Richard

  4. 0
    Paul Harris ·
    The simplest way to convert a P3 schedule to days from hours is to open in SureTrak and change it to a daily schedule in the options form. This only works if the schedule has eight hour day calendars

    If you do this with P3 using the copy function then Global change may be used to divide the durations by the number of hours per day and all the lags will also need fixing up. If there are lots lags then I export to dbf format and fix in Excel & import , after backing up.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers & Consulting
    www.eh.com.au

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?