Problem in showing Target bars

Rehan AbbasiMember for 19 years 11 months
Created
3
14
0
hi,
Thing my friends is that although i am able to view the baseline target bars along with the actual ones, i am just not able to do the same for a new target.
Please help.

3 replies

Oldest first
  1. 0
    Karim Mounir ·
    maybe due to the "Position" of the bars of the new target?
  2. 0
    Rehan Abbasi ·
    Sry didnt get you karim.
  3. 0
    Karim Mounir ·
    rehan,

    Right click on the "Gantt Chart", click on "Bars" --> Dbl click on the bar which isn’t showing.
    A "Modify Bar Definition" window appears, next to the "Description" box u’ll find a list called "Position", select the number u want so that the bars will be shown under each other (ie. make the actual no.1, target1 no.2, target2 no.3).

    HTH

    Regards,
    Karim