Time Visable in ES Date

Jonathan WardMember for 19 years 8 months
Created
2
1
0
Hello,
I want to view only the date in the ES Column of my plan, the time is visable under the date, is there an esay way to hide this info?
Many thanks
Jon

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Hi Jonathan,

    I believed that you are using P3 with planning unit as hour. Goto Format-> Dates... on your P3 menu
    On Time Display select or tick None. That should solve your problem.

    Regards,
    Rodel
  2. 0
    Jonathan Ward ·
    thats great, thank you very much for your help
    regards
    Jon