Activity cancelled but retain in baseline?

Laura JohnstoneMember for 19 years 8 months
Created
2
1
0
Afternoon all

Is there a way to retain an activity’s baseline even though the job itself has been cancelled and won’t be completed?

I don’t want to remove the job from the plan as I need to show that it couldn’t be done due to the overrunning of another activity.

Many thanks
Laura Johnstone

2 replies

Oldest first
  1. 0
    Ife Olyke ·
    Laura,

    You can create an activity code for deleted activities and assign it to that job. Then you can select the activity code in your filter specifications so it doesn’t show. You can also use log records for further notes. I hope this makes sense...Can’t think of anything better unless someone else does..

    Cheers

    Ifeanyi

  2. 0
    Laura Johnstone ·

    Makes perfect sense Ifeanyi. Many thanks for your help.

    Cheers
    Laura