Activity cancelled but retain in baseline?
In the Open Standard
Laura JohnstoneMember for 19 years 8 months
- Created
- 2
- 1
0
Afternoon all
Is there a way to retain an activity’s baseline even though the job itself has been cancelled and won’t be completed?
I don’t want to remove the job from the plan as I need to show that it couldn’t be done due to the overrunning of another activity.
Many thanks
Laura Johnstone
Is there a way to retain an activity’s baseline even though the job itself has been cancelled and won’t be completed?
I don’t want to remove the job from the plan as I need to show that it couldn’t be done due to the overrunning of another activity.
Many thanks
Laura Johnstone
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?