new users in network use
In the Open Standard
Johnny PainMember for 21 years
- Created
- 2
- 3
0
hi everyone !
we don’t have any network licences of P3, so everytime we have to be several of us opening the same project, we :
- store the project on a server
- run NetSet on a computer of the network
- create the users, assign passwords
- assign the access rights to the project
- copy the USERFIL.P3 file on every computer of the network
and it works real fine, except maybe for the speed of the network, which could be -I guess- improved with network licences.
the problem is, we currently use P3 on a 2 computer network. but we don’t have control over the additionnal computers that are going to connect to the network, which are external companies computers.
I tried to access the project from a brand new computer, and what a surprise, we can open the project even if we’re logged under any name. we can see that the only authorized user is the one I’ve created for the occasion, but if I don’t copy the USERFIL.P3 file onto this particular computer, the access rights seem to disappear.
does anyone have any idea of what happens here ?
thank you !
we don’t have any network licences of P3, so everytime we have to be several of us opening the same project, we :
- store the project on a server
- run NetSet on a computer of the network
- create the users, assign passwords
- assign the access rights to the project
- copy the USERFIL.P3 file on every computer of the network
and it works real fine, except maybe for the speed of the network, which could be -I guess- improved with network licences.
the problem is, we currently use P3 on a 2 computer network. but we don’t have control over the additionnal computers that are going to connect to the network, which are external companies computers.
I tried to access the project from a brand new computer, and what a surprise, we can open the project even if we’re logged under any name. we can see that the only authorized user is the one I’ve created for the occasion, but if I don’t copy the USERFIL.P3 file onto this particular computer, the access rights seem to disappear.
does anyone have any idea of what happens here ?
thank you !
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?