Sheduling - Loop
In the Open Standard
J Venkatesh PMP PSP ACIArbMember for 20 years 2 months
- Created
- 4
- 1
0
Hi...
Am using P3.1 and I have liknked all the activities in a project and when I was scheduling (Pressing F9), got a report as schedule termiated..loop detected...
since there are lot of activities, i cudnt able to find the link defect of particular activity...
can anyone suggest, how to find / generate a report showing the defect link / activty..
rgds
venkat
Am using P3.1 and I have liknked all the activities in a project and when I was scheduling (Pressing F9), got a report as schedule termiated..loop detected...
since there are lot of activities, i cudnt able to find the link defect of particular activity...
can anyone suggest, how to find / generate a report showing the defect link / activty..
rgds
venkat
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?