Skip to content

Sheduling - Loop

J Venkatesh PMP PSP ACIArbMember for 20 years 2 months
Created
4
1
0
Hi...

Am using P3.1 and I have liknked all the activities in a project and when I was scheduling (Pressing F9), got a report as schedule termiated..loop detected...

since there are lot of activities, i cudnt able to find the link defect of particular activity...

can anyone suggest, how to find / generate a report showing the defect link / activty..

rgds
venkat

4 replies

Oldest first
  1. 0
    Venkat Ramana ·
    Heyy...

    After scheduling i think you got a report of the loops detected...Actually loops are traced when activities are linked incorrect..i.e example of a loop is A-B-C-D-A..just go to the activity A and check its predecessor or successor and make correction..ur schedule shall be successful.

    Regards,
    VENKAT RAMANA
  2. 0
    J Venkatesh PMP PSP ACIArb ·
    Dear Ramana,

    thanks for ur immediate response...

    but when am scheduling it, am not getting detailed report, just its showing scheduling terminated and loops detected...

    I don kno, whther any installation file wud be missing????
  3. 0
    Hannes de Bruyne ·
    Hello Jaya

    Don’t use F9 for scheduling, use the Icon with the red clock.

    This will give you the report

    Hannes
  4. 0
    J Venkatesh PMP PSP ACIArb ·
    Dear Honnes,

    its worked well...

    thx

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?