Skip to content

updating an activity out of logic

Sinan FahmiMember for 19 years 10 months
Created
4
2
0
Dear All,
can any body tell me is it possible to update an activity which out of logic, for example i planed to start AC ducting work at 1st of june but i started in 25 april?

and how can i update it? is any thing will affect?

thanks for your help......

4 replies

Oldest first
  1. 0
    Akin Adurosakin ·
    Update as you would update any other activity: Actual start date, percentage complete, remaining duration, resource usage etc. However, remember to check the effect of this out of sequence activity on its predecessors/successor; you may have to break and modify the link and introduce some lag. Generally it will not impact on the other activities if the above precautions are taken into consideration.

    Regards,
    Akin
    Nigeria
  2. 0
    Sinan Fahmi ·
    thanks my friend, but what about target plan should i also modify the link or just in i modify in updating program only.

    thnx again
  3. 0
    Akin Adurosakin ·
    No, you do not need to modify your target plan; the target plan is basically for comparison with your running/current plan so don’t modify it. So just modify only the updating/current schedule.

    However, you can decide to create another target with this new plan. Recall that P3 allows you to create as many target projects as you want, though, you can compare only two targets to the current schedule at any one time.

    I hope this helps.

    Regards
    Akin
    Nigeria
  4. 0
    Sinan Fahmi ·
    Thnx you very much i get your answer...

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?