P3 3.1 Layout

Nazarulislam KamaludinMember for 20 years 4 months
Created
4
2
0
Hi,
I got a problem in showing bars in new file. when i add early bars, its not showing. I tried to do in new layout, same thing is repeating. Can anybody tell me, how to rectify this problem.

4 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Nazarulislam,

    Check your bar settings. You might not tick the show box or it maybe overlaping on other bars rows. If you are not sure how to do it, open a project that the layout is working for you then transfer it to your new project. Otherwise let me know if you need assistance in setting a bar.

    Regards,
    Rodel
  2. 0
    Nazarulislam Kamaludin ·
    hi,

    Thanks for u’r reply Mr.Rodel, I also used to open a project with working layout and then i used to transfer. But why this is happening? Whenever i start a new file, my layout is not of classic schedule, but some other layout from my older file.Why it is so?
  3. 0
    Rodel Marasigan ·
    Nazarulislam,

    You may not have a default layout set on P3 but you can make one.
    Follow this step to set a default layout for new projects.
    1) Open a project that having a layout that you want set as default.
    2) Select View-> Layout-> Make Default
    3) If prompted “Replace the default” Click Ok.

    That should set your default layout for new projects.

    Regards,
    Rodel
  4. 0
    Nazarulislam Kamaludin ·
    Thanks, Now i tried u’r options and coming ok. So it was a problem with my default layout.