Format chart to show weekdays and weekends

Terry WhiteMember for 22 years 8 months
Created
1
1
0
I can’t seem to work out how to format the Gannt chart so that the bars can be seen in relation to Weekdays and Weekend days.

It almost seems as though P3 can’t support this way of showing the Gannt chart.

Can anyone advise please ?

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Hi Terry,

    Format Bar then tick Neck on the bars that you want to show the necking and also tick "also neck for" Holiday and Weekends.

    Rodel