Date format in P3

A DMember for 19 years 5 months
Created
11
3
0
Hi guys,

Normally i use foillowing date format in P3 starting with date followed by month and then year

SAy, 23 JAN 08

One of our client has requested (entire team is Korean) to put in format they work with i.e.

080123 - (Year followed by month and then date)

Is it possible to show in P3?

:)

Rav

11 replies

Oldest first
  1. 0
    James Barnes ·
    Raviraj

    yes, it is possible.

    *click* Format>dates

    In the dialog box is a selection of date styles. the one you want, I think, is the bottom one

    I believe this is view specific so you will need to change it in each of your views

    R

    James
  2. 0
    A D ·
    Thanx James,

    How Sometime one can forget the basic things and make the problem look worse ?

    :-)
  3. 0
    Sum Lap Key ·
    Hi all

    I also click* Format>dates. I just select the date format 080123. But I can’t select the date format 23 JAN 08 in my P3 programme. Do you know why?

    Thank you


    Mercer
  4. 0
    Tommy Nug ·
    Hi Sum,
    Can you detail more?
  5. 0
    Sum Lap Key ·


    I mean that when I open P3,Format , then date, I just can choose dates in number format (e.g. 16112007) and I can’t choose the date format like 16Nov2007. Do you know why is that?

    Thank you
  6. 0
    Nar Thap ·
    try this one
    tools>option>project tab--- change date format at Dates
    cheers
  7. 0
    Sum Lap Key ·
    Excuse me, I can’t find the project tab from tools>options in P3.

    Can you give me more hints?
  8. 0
    Tommy Nug ·
    What is your version? In p3.1, We dont have the function showed by Nar
  9. 0
    Sum Lap Key ·
    It is P3.0 version. maybe there is no such function.

    Thank you very much for your information which is very useful.
  10. 0
    A D ·
    I hav P3.0,

    Just go to Format --> Dates.

    U can select the required format.

    Cheers,

    Rav
  11. 0
    Tommy Nug ·
    Correct! The problem here is your version differs from what others have. Sometimes, a very simple function can cause a little bit problem when you are a beginner!

Log in or join to reply