Actual activity drives its succcessor
In the Open Standard
Osman CeranMember for 19 years 6 months
- Created
- 3
- 3
0
Dear Friends
I come across with a problem resulting from driving activities.
The activities that have actual start and finish dates drice their successor activities since their predecessors are not actual.
Let me explain wit a simple example
C200 Construction / P200 Procurement Phase-2 / P100 Procurement Phase-1
P200 drives its successor C200 altough P200 has actual start and finish dates. However P200’s predecessor P100 is not actual.
Your advice regarding the issue will be highly appreciated.
Thanks
Osman
I come across with a problem resulting from driving activities.
The activities that have actual start and finish dates drice their successor activities since their predecessors are not actual.
Let me explain wit a simple example
C200 Construction / P200 Procurement Phase-2 / P100 Procurement Phase-1
P200 drives its successor C200 altough P200 has actual start and finish dates. However P200’s predecessor P100 is not actual.
Your advice regarding the issue will be highly appreciated.
Thanks
Osman
3 replies
Oldest firstLog in or join to reply