What is the use of Alias in Act codes ?

Pranab Kumar DebMember for 19 years 8 months
Created
2
1
0
Can some body enligten me on what is the Use of Alias in activity code?
regards
deb

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Deb,

    Aliases are used to summarize and select activities for tabular reports and graphics at a more specific level than is possible with single codes.

    It is a combined activity codes or activity ID codes up to five combinations.
    Once you create an alias, it appears with other activity codes in drop-down lists.
    Ex: MNGR = PHASE + DEPARTMENT + RESPONSIBILITY creates an alias for MANAGER.
    Alias =: Enter a name for the alias code.
    Code 1/+Code 2/+Code 3/+Code4/+Code 5: Enter the codes that you want to combine to create the alias.

    Rodel
  2. 0
    Pranab Kumar Deb ·
    Thanks Rodel for the info
    regards
    deb