How to show suspended activity in the bar chart

Mark Anthony CortezMember for 19 years 6 months
Created
2
5
0
I come across a problem of showing in a bar chart of suspended activity.i have a concrete slab activity and it could not be done continously in my schedule,i have to start and work for a period of 8 days,the stop & resume after 5 days.and continue for another 22 days,this i cant display in the bar chart,i tried it to use suspend date but of no avail.the program is asking for actual start date.please any body can help me?

Thanks a lot,

Mark

2 replies

Oldest first
  1. 0
    Ashraf Jahangeer ·
    Hi Mark,

    It was an interesting excercise however I tried one solution which may suit you.

    You can define a seperate calender for the above actvity and show the days as non working for as many days as you like to suspend it.

    Regards,

    Ashraf
  2. 0
    Ife Olyke ·
    You could have a different calendar id for that activity, where you define the holiday periods. Then go to format => bars => early bars => check box for "neck" and "holidays". Good luck.