Dear all,

How to copy one of the activity description into another row in order not to repeat and saving time?

regards,

Moutaz

2 replies

Oldest first
  1. 0
    Ashraf Jahangeer ·
    Insert as many activities as you like leaving the description blank.

    Select the activity description including the one you want to copy. Right click the mouse and press fill cell.

    Regards,

    Ashraf
  2. 0
    Moutaz Aldeib ·
    Thanks Ashraf,

    It is working.