Activity Limits Exceeds

Lorenzo TolentinoMember for 19 years 5 months
Created
4
2
0
please help...whenever i try to open a file coming from my colleague a dialogue box appear saying "activity limits exceeds" and it does’nt open. this project schedule contains only about 260 activities.pls give some information about this matter...tnx and best regards

Renz

4 replies

Oldest first
  1. 0
    Ashraf Jahangeer ·
    Hi Renz,

    It has something to do with length of Activity ID and this file must contain a number of sub-projects. Try to open the sub-project seperately and hopefully you may succeed.

    Regards,

    Ashraf
  2. 0
    Pranab Kumar Deb ·
    hello Lorenzo Tolentino ,
    Hope you are not using the trial version of P3 , this message generally comes when trial version of p3 software is used.
    regards
    deb
  3. 0
    Lorenzo Tolentino ·
    Tnx a lot Mr. Pranab Kumar Deb, your suggestion really helped me a lot to solve the problem. Have a nice fay. Godbless
  4. 0
    Renjith B ·
    Hi,

    Try it once more with the file sitting directly in one of your hard drives.


    Renjith