Resource Calculation_Not Functioning Well

Zq qzMember for 23 years 4 months
Created
1
2
0
I have problem with my SCH. for resource with budget cost / unit price >9,999,999. P3 will not calculate (BQ x Unit Price ).

Message below shown while doing the F9/calculation.

Numbers too large in calculation for activity DLVU0110 resource AP0110A , cost not computed.

Can you help me how to fix this problem.

1 reply

Oldest first
  1. 0
    Pranab Kumar Deb ·
    Hello Ferdi Nand,
    I think you have to go for Putting the Unit price for all the items to 1000’s i mean your unit rate will become 9,999.99.
    HTH
    Deb