Global Change - Resource Driving Flag

Kevin DonaghyMember for 23 years 4 months
Created
4
1
0
Hi planners,

Does any one out there know how I would do a global change to remove the driving flag from my resources in a schedule?

I imported a schedule from P5 to P3, and the resources are all driven, and I want to change task durations, which I can only do if I remove the driven flag, but doing task by task is painful.

Cheers, Kevin

4 replies

Oldest first
  1. 0
    Smiling Shagger ·
    use a rubber
  2. 0
    A D ·
    A Rubber. Do u know whats d meaning of "RUBBER".

    U make us smile u smiling shagger
  3. 0
    Ronald Romero ·
    Hi Kevin,

    Use this Rdrv eq " "

    Cheers,
    Ronnie
  4. 0
    Kevin Donaghy ·
    Hi Ronald,

    Thanks that worked ;-)

    Sorry Shagger, might use your suggestion next time ;-)

    Kevin