Global Change - Resource Driving Flag
In the Open Standard
Kevin DonaghyMember for 23 years 4 months
- Created
- 4
- 1
0
Hi planners,
Does any one out there know how I would do a global change to remove the driving flag from my resources in a schedule?
I imported a schedule from P5 to P3, and the resources are all driven, and I want to change task durations, which I can only do if I remove the driven flag, but doing task by task is painful.
Cheers, Kevin
Does any one out there know how I would do a global change to remove the driving flag from my resources in a schedule?
I imported a schedule from P5 to P3, and the resources are all driven, and I want to change task durations, which I can only do if I remove the driven flag, but doing task by task is painful.
Cheers, Kevin