Job Cards from Plan

Milton MaindonaldMember for 19 years 3 months
Created
2
1
0
Is it possible to produce Job Cards from a plan?
E.g. Using the "Spotlight Function"; could a Jobcard be produced for all the Highlighted Activities?

2 replies

Oldest first
  1. 0
    Anoon Iimos ·
    i guess yes, but that would depend on the tasks, i.e. descriptions and durations; maybe you need your job cards daily, then you’ll need lots of details as well
  2. 0
    Marcel van der Leij ·
    On a previous project I exported the activity data with a "1-week look-ahead filter" to Excel/Access. From there on you can add fields for actual ressources/manhours used, delays encountered etc. By using Access reports your printing possibilities are virtually unlimited.
    The intrinsic advantage of the jobcards of course is the organized and disciplined progress reporting (once you have educated the individuals involved!)
    In addition you end up with a database containing all the project history linked to the Primavera activities. The forensic schedulers loved it!

    Cheers, Marcel